Project Management- Trade off Implications


Implications of Tradeoffs on projects




Introduction



The trade-off decisions are made all across the project life cycle which varies considerably. This is especially true if we specifically talk about scope, schedule and cost. One of the most typical progressions that I see begins with planning our projects within a set budget and a fixed schedule. Once the project is defined and planned, those requirements and the plan itself are under formal change control so we can’t mess with them without more formal consideration and approval. In many organizations, that nuance gets lost along the way. This paper primarily focuses on the implications of the tradeoffs made at various stages of project life cycle and few examples will be presented. [1]


Discussion



Most projects have trade off relationship between the time taken to complete a task and the cost of said task. In general, this relationship will be driven by an proportional relationship: taking too long will increase the cost as wages and other costs will increase; and an inversely proportional relationship: reducing the time requirement sharply is likely to increase costs as more direct materials, overtime and other resources must be directed towards the task. As such, there generally exists an optimal time for any task, at which overall costs are minimized. [1]


In case of metro bus project (in Lahore), we witnessed some serious tradeoffs which are now being criticized. [4] Some were in the form of scope whereas others were in the form of costs and time. In my opinion, the planners planned the scope of this project in such as way that it satisfies the hidden need along with the need of transportation. Considering that the numbers of road accidents have significantly reduced after the implementation of this project, it seems as if the primary objective was to reduce the road accidents; but as long as the need in not realized there is no point designing the scope of projects in accordance with the hidden need. Due to which this project faced lot of criticism and people started calling it as “Jangla Bus”. [3] There was a need to first realize this actual need and then effort had to be made to solve this need or to make the awareness about the need which is being solved. If this had been the case then lot of criticism could have been ignored. [2] In addition, this particular project had tremendous direct costs directly associated with the activity level of a task or project; which are often referred to as variable costs. For example, it included hourly wages, and materials etc. This project was planned to be completed within shorter period of time. In the process huge trade off was made as whenever the speed of a task is increased, direct costs generally increase also, due to the law of diminishing returns. Where there was a need to employ fewer work forces, they had to employ much more than the standard level. Not only this the additional overtime premiums had to be paid to nearly every worker as lot of overtime was needed to complete the project in given time. According to Punjab Government, approximately Rs. 30 billion were spent. Subsequently, billions of rupees were wasted to complete this project in shorter period of time.  Normally if a project is at risk of delays, the schedule can often be compressed, or crashed, through the investment of more resources and an increase in direct costs; but this should only be done as long as you are unable to meet the requirements. In order to determine the optimal project time and cost, a project manager of Metro Bus project should have understood the minimum time in which a task can be completed and how much this will cost as well as the normal time in which a task could be completed with minimum cost; and how the costs will vary with the time taken. If we analyze this particular project we will find millions of rupees wasted only because mismanagement of tradeoffs. Considering that the total annual budget (for the year 2012-2013) of health and education in Punjab is about Rs. 25 billion and Rs. 25 billion respectively and Punjab is less than the total amount invested on this particular project, we must say that for this mismanagement of tradeoff we had to pay highest level of cost in terms of opportunity cost. [5]


Conclusion



In situations you may need more project management resources such as money and/or resources and/or time to manage the project, due to which sometimes tradeoff becomes a need. This risk can also impact the ability to meet the customer requirements. In addition to risks, other changes can occur on your project for any number of different reasons. This is when you’ll need to examine the project trade-offs. To examine the project trade-offs, we have to be clear about the impact that any change will have on the project-whether it be more time, budget, resources, etc. as every tradeoff made might result in some serious implications.  


No comments:

Post a Comment

Followers